The Campus Construction Update will become a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices.
Week of May 15th
Start Piping Install in CHUTE and RUMINANT Buildings. (Chance of minor noise with this work)
Demolition to continue in DAIRY, LANGILLE and HALEY Buildings. (Chance of minor noise with this work)
Isolation and draining to start in HALEY NORTH, HALEY SOUTH, HALEY AQUACULTURE, JENKINS HALL and possibly part of CUMMING HALL. (Note: heating will be shut off in these buildings)
Week of May 23rd
Piping Installation to continue in RUMINANT building and start in BOULDING and DAIRY Buildings. (Chance of minor noise with this work)
Demolition continues in HALEY and JENKINS HALL. (Chance of minor noise with this work)
Any questions or concerns please contact:
Stephanie MacKenzie
Project Manager Facilities Management
902.956.4492
Stephanie.Mackenzie@dal.ca
Recent News
- 2027 ACORN Annual Conference & Trade Show
- Get to Know the Master Gardener Team!
- Suresh Raja’s Keynote Talk in Brazil
- Diwali Night 2026 Brings Culture, Celebration and Community Together at ÌÇÐĹÙÍøhousie Agricultural Campus
- Strengthening Canada‑Egypt Ties Through Agricultural Knowledge Exchange
- Atlantic Agricultural Hall of Fame Inducts four members
- Recognize a Facilities Management Employee
- International Education Week ‑ Potluck